Opportunity summary

Source-cited

The US Fish and Wildlife Service requires Bunkhouse Fire Alarm Replacement at Hart MTN Lakeview, OR, with a magnitude of construction under $10,000. The solicitation is posted through August 25, 2026, with a response deadline of September 7, 2026. [4]

Key points

  • NAICS code is 238210; small business standard is $19 Million. [4]
  • Contractor must notify the Contracting Officer of differing site conditions. [1]

Watch items

  • Deliverables and/or Delivery Schedule are specified. [2]
  • Offerors must complete and submit listed provisions. [3]

Sources

  1. Sol_140FC126Q0036.pdf140FC126Q0036 FWS (a) The Contracting Officer may order changes in the drawings and specifications within the scope of the contract in writing. (b) The Contractor shall promptly notify the Contracting Officer, in writing, of subsurface or latent physical conditions differing materially from those indicated in this contract or unknown unusual physical conditions at the site before proceeding with the work. (c) If changes under paragraph (a) of this clause or conditions under paragraph (b) of this clause increase or decrease the cost of, or time required for performing the work, the Contracting Officer shall make an equitable adjustment (see paragraph (d) of this clause) upon submittal of a pr
  2. A04_SOW.pdf4) Deliverables and/or Delivery Schedule A.
  3. Sol_140FC126Q0036.pdfThe offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer.
  4. Official SAM.gov noticePosted Aug 25, 2026; Responses due Sep 7, 2026, 1:00 PM UTC; Archive date Sep 22, 2026

Generated from the public notice and source-backed solicitation passages. Confirm important requirements in the cited brief and official documents.

Public-source intelligence

Source-backed opportunity brief

6 citations · 6 sources

By November 30, the Contractor shall revise the report, or put its reason in writing for the agency. (f) First-tier subcontracts. (1) The Contractor shall require each first-tier subcontractor providing services under this contract, with subcontract(s) each valued at or above the thresholds set forth in 4.303(b), to provide the following detailed information to the Contractor in sufficient time to submit the report: (i) Subcontract number (including subcontractor name and unique entity identifier); and (ii) The number of first-tier subcontractor direct-labor hours expended on the services performed during the previous Government fiscal year. (2) The Contractor shall tell the subcontractor that the information will be made available to the public as required by section 743 of Division C of the Consolidated Appropriations Act, 2010. (End of clause) 52.213-4 Terms and Conditions—Simplified Acquisitions (Noncommercial) (OCT 2025) (DEVIATION MAR 2026) As prescribed in 13.204(b), insert the following clause: (a) Inspection/Acceptance.

Scope

140FC126Q0036 FWS (a) The Contracting Officer may order changes in the drawings and specifications within the scope of the contract in writing. (b) The Contractor shall promptly notify the Contracting Officer, in writing, of subsurface or latent physical conditions differing materially from those indicated in this contract or unknown unusual physical conditions at the site before proceeding with the work. (c) If changes under paragraph (a) of this clause or conditions under paragraph (b) of this clause increase or decrease the cost of, or time required for performing the work, the Contracting Officer shall make an equitable adjustment (see paragraph (d) of this clause) upon submittal of a proposal for adjustment (hereafter referred to as proposal) by the Contractor before final payment under the contract. (d) The Contracting Officer shall not make an equitable adjustment under paragraph (b) of this clause unless— (1) The Contractor has submitted the required written notice and the Contracting Officer has received the notice; or (2) The Contracting Officer waives the requirement for written notice. (e) Failure to agree to any adjustment shall be a dispute under the Disputes clause. (End of clause) 52.247-69 REPORTING REQUIREMENT FOR U.S.-FLAG AIR CARRIERS REGARDING TRAINING TO PREVENT HUMAN TRAFFICKING (JAN 2025) a) Definitions.

Evaluation

If the concern waives the preference, the factor will be added to its offer for evaluation purposes. □ Offeror chooses to waive the evaluation preference. (c) Joint venture.

Submission

The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer.

Extracted from the official notice and archived solicitation files. Confirm controlling requirements in the source documents.

Notice information

Read full notice text

The US Fish and Wildlife Service has a requirement for Bunkhouse Fire Alarm Replacement at Hart MTN Lakeview, OR. The bases of award will be lowest price fair and reasonable NAICS code is 238210 and the small business size standard is $19 Million. The magnitude of construction is Less than $10,000

What changed

Aug 25, 2026 · 2 fields changed
TitleOR HART MTN ANTLP RFG BUNKHOUSE FIRE ALAZ--OR HART MTN ANTLP RFG BUNKHOUSE FIRE ALA
Documents46

Notice history

Attachments

Open a filename to view the saved source file. If a saved copy is not available yet, FedRoster will continue to the matching SAM.gov notice.

Back to top ↑