Opportunity summary
Source-citedThe US Fish and Wildlife Service requires Bunkhouse Fire Alarm Replacement at Hart MTN Lakeview, OR, with a magnitude of construction under $10,000. The solicitation is posted through August 25, 2026, with a response deadline of September 7, 2026. [4]
Key points
- NAICS code is 238210; small business standard is $19 Million. [4]
- Contractor must notify the Contracting Officer of differing site conditions. [1]
Watch items
- Deliverables and/or Delivery Schedule are specified. [2]
- Offerors must complete and submit listed provisions. [3]
Sources
- Sol_140FC126Q0036.pdf
140FC126Q0036 FWS (a) The Contracting Officer may order changes in the drawings and specifications within the scope of the contract in writing. (b) The Contractor shall promptly notify the Contracting Officer, in writing, of subsurface or latent physical conditions differing materially from those indicated in this contract or unknown unusual physical conditions at the site before proceeding with the work. (c) If changes under paragraph (a) of this clause or conditions under paragraph (b) of this clause increase or decrease the cost of, or time required for performing the work, the Contracting Officer shall make an equitable adjustment (see paragraph (d) of this clause) upon submittal of a pr
- A04_SOW.pdf
4) Deliverables and/or Delivery Schedule A.
- Sol_140FC126Q0036.pdf
The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer.
- Official SAM.gov notice
Posted Aug 25, 2026; Responses due Sep 7, 2026, 1:00 PM UTC; Archive date Sep 22, 2026
Generated from the public notice and source-backed solicitation passages. Confirm important requirements in the cited brief and official documents.
Public-source intelligence
Source-backed opportunity brief
6 citations · 6 sourcesBy November 30, the Contractor shall revise the report, or put its reason in writing for the agency. (f) First-tier subcontracts. (1) The Contractor shall require each first-tier subcontractor providing services under this contract, with subcontract(s) each valued at or above the thresholds set forth in 4.303(b), to provide the following detailed information to the Contractor in sufficient time to submit the report: (i) Subcontract number (including subcontractor name and unique entity identifier); and (ii) The number of first-tier subcontractor direct-labor hours expended on the services performed during the previous Government fiscal year. (2) The Contractor shall tell the subcontractor that the information will be made available to the public as required by section 743 of Division C of the Consolidated Appropriations Act, 2010. (End of clause) 52.213-4 Terms and Conditions—Simplified Acquisitions (Noncommercial) (OCT 2025) (DEVIATION MAR 2026) As prescribed in 13.204(b), insert the following clause: (a) Inspection/Acceptance.
Scope
140FC126Q0036 FWS (a) The Contracting Officer may order changes in the drawings and specifications within the scope of the contract in writing. (b) The Contractor shall promptly notify the Contracting Officer, in writing, of subsurface or latent physical conditions differing materially from those indicated in this contract or unknown unusual physical conditions at the site before proceeding with the work. (c) If changes under paragraph (a) of this clause or conditions under paragraph (b) of this clause increase or decrease the cost of, or time required for performing the work, the Contracting Officer shall make an equitable adjustment (see paragraph (d) of this clause) upon submittal of a proposal for adjustment (hereafter referred to as proposal) by the Contractor before final payment under the contract. (d) The Contracting Officer shall not make an equitable adjustment under paragraph (b) of this clause unless— (1) The Contractor has submitted the required written notice and the Contracting Officer has received the notice; or (2) The Contracting Officer waives the requirement for written notice. (e) Failure to agree to any adjustment shall be a dispute under the Disputes clause. (End of clause) 52.247-69 REPORTING REQUIREMENT FOR U.S.-FLAG AIR CARRIERS REGARDING TRAINING TO PREVENT HUMAN TRAFFICKING (JAN 2025) a) Definitions.
Deliverables
4) Deliverables and/or Delivery Schedule A.
Evaluation
If the concern waives the preference, the factor will be added to its offer for evaluation purposes. □ Offeror chooses to waive the evaluation preference. (c) Joint venture.
Submission
The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer.
Key dates
Posted Aug 25, 2026; Responses due Sep 7, 2026, 1:00 PM UTC; Archive date Sep 22, 2026
Extracted from the official notice and archived solicitation files. Confirm controlling requirements in the source documents.