Opportunity summary
Source-citedThis is a Firm-Fixed Price construction opportunity for Pole Barn Insulation in MN Valley NWR, with a magnitude between $100,000 and $250,000. Quotes are due by September 10, 2026, and a site visit is encouraged on August 31, 2026. [1]
Key points
- Contract type is Firm-Fixed Price for construction. [1]
- Performance period is 45 Calendar Days after NTP. [1]
Watch items
- Site visit is scheduled for August 31, 2026. [1]
- Questions are due September 4, 2026, at 1100 CT. [1]
Sources
- Official SAM.gov notice
Posted Aug 25, 2026; Responses due Sep 10, 2026, 4:00 PM UTC; Archive date Sep 25, 2026
Generated from the public notice and source-backed solicitation passages. Confirm important requirements in the cited brief and official documents.
Public-source intelligence
Source-backed opportunity brief
6 citations · 6 sources140FC226Q0047 FWS (i) Is for supplies, other than commercially available off-the-shelf items, acquired outside the United States, or services to be performed outside the United States; and (ii) Has an estimated value that exceeds $700,000. (2) The Contractor must maintain a compliance plan during the performance of the contract that is appropriate— (i) To the size and complexity of the contract; and (ii) To the nature and scope of the activities to be performed for the Government, including the number of non-United States citizens expected to be employed and the risk that the contract or subcontract will involve services or supplies susceptible to trafficking in persons. (3) Minimum requirements.
Scope
Unless this is a contract for the acquisition of commercial products or commercial services, the Contractor shall include the requirements of this clause, including this paragraph (e) (appropriately modified for the identification of the parties), in each subcontract that— (1) Exceeds the threshold specified in FAR 9.405-2(b) on the date of subcontract award; and (2) Is not a subcontract for commercially available off-the-shelf items. (End of clause) 52.209-10 Prohibition on Contracting With Inverted Domestic Corporations (NOV 2015) (DEVIATION MAY 2026) (a) Definitions.
Deliverables
F.2.0 PROGRESS PLAN At the prework conference, the Contractor shall provide to the COR a written "work progress plan" that details its proposed work force and schedule to provide for orderly completion of the work within the contract performance time.
Evaluation
L.2.1.3 Evaluation Factor, Past Performance.
Submission
The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer.
Key dates
Posted Aug 25, 2026; Responses due Sep 10, 2026, 4:00 PM UTC; Archive date Sep 25, 2026
Extracted from the official notice and archived solicitation files. Confirm controlling requirements in the source documents.