Scope
The contractor shall consider in the quote all aspects related to this scope of work including but not limited to safety requirements, insurance, materials, equipment, etc.
STATE, DEPARTMENT OF · STATE, DEPARTMENT OF · U.S. EMBASSY QUITO
This RFP seeks proposals for upgrading the residential electrical distribution and backup power system at the U.S. Embassy Quito compound in Ecuador. The contract requires providing all necessary engineering, labor, and construction services for this electrical system upgrade. [1][2]
76 4.0 GENERAL REQUIREMENTS 4.1 4.1 The Contractor shall provide all engineering services, labor, supervision, equipment, tools, materials (except Government-Furnished Equipment (GFE)), and construction services necessary to complete the extension of the medium-voltage electrical distribution system, including the implementation of a three-phase network, replacement of the existing transformer, installation of generators and associated systems, and all required civil works.
Proof of SAM Registration Offerors shall be registered in the SAM (System for Award Management) database at https://www.sam.gov prior to submittal of their offer/proposal as prescribed under FAR 4.1102.
Generated from the public notice and source-backed solicitation passages. Confirm important requirements in the cited brief and official documents.
76 4.0 GENERAL REQUIREMENTS 4.1 4.1 The Contractor shall provide all engineering services, labor, supervision, equipment, tools, materials (except Government-Furnished Equipment (GFE)), and construction services necessary to complete the extension of the medium-voltage electrical distribution system, including the implementation of a three-phase network, replacement of the existing transformer, installation of generators and associated systems, and all required civil works.
The contractor shall consider in the quote all aspects related to this scope of work including but not limited to safety requirements, insurance, materials, equipment, etc.
(a) “Contract Drawings or Drawings,” where indicated by the context, means those drawings specifically listed in the construction contract or as later incorporated into the contract by contract modification. (b) “Day” means a calendar day unless otherwise specifically indicated. (c) “Host Country” means the country in which the project is located. (d) “Material” means all materials, fixtures and other articles incorporated in, or which are intended to remain with, the project. (e) “Notice to Proceed” means a written notice to the Contractor from the Contracting Officer authorizing the Contractor to proceed with the work under the contract as of a date set forth in the Notice. (f) “Other Submittals” includes progress schedules, shop drawings, testing and inspection reports, and other information required by the contract to be submitted by the Contractor for information or approval by the Government. (g) “Project Data” includes standard drawings, diagrams, layouts, schematics, descriptive literature, illustrations, schedules, performance and test data, and similar materials furnished by the Contractor to explain in detail specific portions of the work required by the contract. (h) “Samples” are physical examples which illustrate materials, equipment or workmanship and establish standards by which the work will be judged. (i) “Schedule of Defects” means the list of items, prepared in connection with substantial completion of the work or early occupancy or utilization of a portion thereof, which the Contracting Officer has designated as remaining to be performed, completed or corrected before the work will be accepted by the Government. (j) “Separate Contractor” means a contractor, other than the Contractor or any of its subcontractors, to whom the Government has awarded a contract for construction of a portion of the project. (k) “Work” means any and all permanent construction which is intended to be incorporated into the finished project and required to be performed or otherwise provided by the Contractor under this contract, unless otherwise indicated by the context.
71 SECTION M - EVALUATION FACTORS FOR AWARD M.1 EVALUATION OF PROPOSALS
Proof of SAM Registration Offerors shall be registered in the SAM (System for Award Management) database at https://www.sam.gov prior to submittal of their offer/proposal as prescribed under FAR 4.1102.
Quito, EC-P, ECU
Posted Aug 19, 2026; Responses due Sep 4, 2026, 9:00 PM UTC; Archive date Oct 15, 2026
Extracted from the official notice and archived solicitation files. Confirm controlling requirements in the source documents.
Dear Prospective Quoter: Subject: Request for Proposals number 19EC7526R0005 Enclosed is a Request for Proposals (RFP) for Residential Electrical Distribution and backup power system upgrade for U.S. Embassy Quito at Government Owned Residential compound Ziba. If you would like to submit a proposal, follow the instructions in Section L of the solicitation, complete the required portions of the attached document, and submit it to the address shown on Standard Form 1442 that follows this letter. The U.S. Government intends to award a contract/purchase order to the responsible company submitting an acceptable offer at the lowest price. We intend to award a contract/purchase order based on initial Proposals, without holding discussions, although we may hold discussions with companies in the competitive range if there is a need to do so. The Embassy intends to conduct a pre-proposal conference at the site, The pre-proposal conference will be held on August 3, 2026, at 11:00 am Quito Time at Ziba residences compound located located in Cumbayá, at the intersection of Humberto Fierro and Cesar Borja streets. Prospective offerors should contact quitoprocurement@state.gov for additional information or to arrange entry to the residences. Direct any questions regarding this solicitation in writing to Mr. Matthew Madden, Contracting Officer to quitoprocurement@state.gov before August 11, 2026, at 16:00 hours Quito time. Proposals are due by September 4, 2026 before 16:00 hours Quito time. No Proposals will be accepted after this time. Proposals must be in English and incomplete proposals will not be accepted. Your proposal must be submitted electronically to quitocontracts@state.gov, It is important to make sure the submission is made in specific size and format; in MS-Word 2007/2010 or MS-Excel 2007/2010 or Adobe Acrobat (pdf) file format. The file size must not exceed 30MB. If the file size should exceed 30MB, the submission must be made in separate files and attached to separate emails with less than 30MB each. The technical and economic proposals must be submitted separately. Do not include pricing within the technical proposal. Failure to that may deem the offeror's proposal to be considered non-responsive. In order for a proposal to be considered, you must also complete and submit the following: 1. SF-1442 2. Section B, Pricing 3. Section K Representations and Certifications 4. Additional information as required in Section L 6. Proof of SAM Registration Offerors shall be registered in the SAM (System for Award Management) database at https://www.sam.gov prior to submittal of their offer/proposal as prescribed under FAR 4.1102. Failure to be registered at time of bid submission shall deem the offeror's quote to be considered non-responsible to the solicitation instructions and requirement and no further consideration will be given. Therefore, offerors are highly encouraged to register immediately if they are interested in submitting a response to this requirement.
Open a filename to view the saved source file. If a saved copy is not available yet, FedRoster will continue to the matching SAM.gov notice.