Scope
Contractor shall submit a request to interrupt any such services to the COR, in writing, no less than 14 calendar days in advance of proposed interruption.
VETERANS AFFAIRS, DEPARTMENT OF · VETERANS AFFAIRS, DEPARTMENT OF · 252-NETWORK CONTRACT OFFICE 12 (36C252)
This solicitation requires a contractor to perform renovations to enable steam supply isolation using double block and bleed valve assemblies across 25 listed buildings in North Chicago, IL. The contract is a Service-Disabled Veteran-Owned Small Business (SDVOSB) Set-Aside, with a response deadline of September 14, 2026. [4]
Contractor shall submit a request to interrupt any such services to the COR, in writing, no less than 14 calendar days in advance of proposed interruption.
The contractor shall provide biweekly (or weekly based on progress meeting interval) computer-produced time, cost, and resource schedules and reports generated from project updates.
The formal certification must be completed, signed and returned with the offeror’s bid, quotation, or proposal.
Set-aside: Service-Disabled Veteran-Owned Small Business (SDVOSB) Set-Aside (FAR 19.14)
Generated from the public notice and source-backed solicitation passages. Confirm important requirements in the cited brief and official documents.
36C25226B0035 Page 23 of 49 (iii) A description of the products or services that the Contractor identifies or has reason to suspect is prohibited (include brand; model number, such as the original equipment manufacturer (OEM) number, manufacturer part number, or wholesaler number; and item description, as applicable); (iv) The entity that produced the product or service (include entity name, unique entity identifier, Contractor and Government Entity (CAGE) code, facilities responsible for design, fabrication, assembly, packaging, and test of the product, and whether the entity was the OEM or a distributor (provide manufacturer codes and distributor codes used for the product)); (v) Description of the functionality of the product or service and how that functionality impacts the risk to the product or service; (vi) An explanation of any factors relevant to determining if the product or service should be permitted by an applicable exception, exemption, or waiver (if the offeror would like the Government to consider a waiver); (vii) Whether alternative products or services are available that would be compliant with the prohibition; (viii) If the product or service is related to item maintenance, include the following information on the item being maintained: (A) Brand; (B) Model number, OEM number, manufacturer part number, or wholesaler number; and (C) Item description, as applicable. (ix) Any readily available information about mitigation actions undertaken or recommended. (2) If a disclosure is required to be submitted to a contracting office, the offeror shall submit the disclosure as follows: (i) If a Department of Defense contracting office, the offeror shall submit the disclosure to the website at https://dibnet.dod.mil. (ii) For all other contracting offices, the Offeror shall submit the disclosure to the Contracting Officer. (3) If the disclosure provided does not contain any of the information required by paragraph (1), and the Offeror later discovers new information that is required by paragraph (1), then the Offeror shall submit a subsequent disclosure within 72 hours of discovering the new information. (h) Executive agency review of disclosures.
Contractor shall submit a request to interrupt any such services to the COR, in writing, no less than 14 calendar days in advance of proposed interruption.
The contractor shall provide biweekly (or weekly based on progress meeting interval) computer-produced time, cost, and resource schedules and reports generated from project updates.
36C25226B0035 Page 39 of 49 the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(B)(1) of this clause. (3) The procedures in paragraph (b)(3)(i)(B)(2) of this clause will no longer apply as of January 1, 2030. (ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or (iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality. (c) Request for determination of inapplicability of the Buy American statute. (1)(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including- (A) A description of the foreign and domestic construction materials; (B) Unit of measure; (C) Quantity; (D) Price; (E) Time of delivery or availability; (F) Location of the construction project; (G) Name and address of the proposed supplier; and (H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause. (ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause. (iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued). (iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award.
The formal certification must be completed, signed and returned with the offeror’s bid, quotation, or proposal.
Set-aside: Service-Disabled Veteran-Owned Small Business (SDVOSB) Set-Aside (FAR 19.14)
North Chicago, IL, 60064, USA
Posted Aug 18, 2026; Responses due Sep 14, 2026, 2:00 PM UTC; Archive date Dec 1, 2026
Extracted from the official notice and archived solicitation files. Confirm controlling requirements in the source documents.
Contractor shall provide all tools, materials, labor, quality assurance, and supervision for renovations resulting in a complete, compliant, and fully-functional project as described throughout the contract documents - including the drawings and specifications. The purpose of this project is to enable complete and compliant isolation and de-energization of the steam supply and condensate return connections using a double block and bleed valve assembly at each entry and exit point of each of the 25 listed buildings.