← Active opportunities
OpenSolicitationAmended

USCG Sector Delaware Bay Shower Replacement

Solicitation number70Z027-26-R-00008

HOMELAND SECURITY, DEPARTMENT OF · US COAST GUARD · TRACEN CAPE MAY(00042)

View opportunity on SAM.gov ↗
Response deadlineSep 9, 2026, 7:00 PM UTC
Deadline status6 days remaining
PostedAug 28, 2026
Record refreshedSep 2, 2026
Place of performancePA, 19147, United States

Opportunity summary

Source-cited

This solicitation is for replacing 15 showers in their entirety, requiring the contractor to supply all necessary personnel and equipment. The response deadline is September 9, 2026, and it is designated as a Small Business Set Aside. [3]

Key points

  • Contractor must provide all necessary personnel and equipment. [3]
  • Deliverables include a Final Project & Safety Plan and weekly reports. [2]

Watch items

  • Updates were made to answer questions regarding bid bonds. [3]
  • The contractor must only tender items conforming to contract requirements. [1]

Sources

  1. Construction+RFQ+Template+(RFO)+June+with+52.222-90.pdfThe Contractor shall only tender for acceptance those items that conform to the requirements of this contract.
  2. SDB+SOW+Shower+renovaton_revised.pdfDeliverable / Milestone Due By 1 - Final Project & Safety Plan Date of Notice to Proceed 2 - Material Specification Sheets TBD by QAE 3 - Weekly Progress Reports Every Friday 4 - Milestone Check: Demolition Complete TBD by QAE 5 - Milestone Check: Installation Complete TBD by QAE 6 2.3.2 Final Walkthrough & Inspection Prior to contract completion 7 2.4 Warranty Documentation Upon project completion 5.0 ACCESS, BADGING, AND SECURITY REQUIREMENTS PR #: 37050PR260000043 STATEMENT OF WORK LAST UPDATED: 24/AUG/2026 PAGE 5/9 • 5.1 Employee Identification
  3. Official SAM.gov noticeSet-aside: Small Business Set Aside - Total

Generated from the public notice and source-backed solicitation passages. Confirm important requirements in the cited brief and official documents.

Public-source intelligence

Source-backed opportunity brief

8 citations · 6 sources

IPP is available at no cost to any commercial vendor or independent contractor doing business with a participating government agency.

Deliverables

Deliverable / Milestone Due By 1 - Final Project & Safety Plan Date of Notice to Proceed 2 - Material Specification Sheets TBD by QAE 3 - Weekly Progress Reports Every Friday 4 - Milestone Check: Demolition Complete TBD by QAE 5 - Milestone Check: Installation Complete TBD by QAE 6 2.3.2 Final Walkthrough & Inspection Prior to contract completion 7 2.4 Warranty Documentation Upon project completion 5.0 ACCESS, BADGING, AND SECURITY REQUIREMENTS PR #: 37050PR260000043 STATEMENT OF WORK LAST UPDATED: 24/AUG/2026 PAGE 5/9 • 5.1 Employee Identification

Evaluation

If a postaward debriefing is given to requesting Offerors, the Government will disclose the following information, if applicable: (1) The agency’s evaluation of the significant weak or deficient factors in the debriefed Offeror’s offer. (2) The overall evaluated cost or price and technical rating of the successful Offeror and the debriefed Offeror and past performance information on the debriefed Offeror. (3) The overall ranking of all Offerors when any ranking was developed by the agency during source selection. (4) A summary of the rationale for award. (5) For acquisitions of commercial products, the make and model of the product to be delivered by the successful Offeror. (6) Reasonable responses to relevant questions posed by the debriefed Offeror as to whether the agency followed source-selection procedures set forth in the solicitation, applicable regulations, and other applicable authorities. (End of provision) FAR 52.212-2 EVALUATION—COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (AUG 2025) (DEVIATION 25-21) (a) Evaluation factors.

Extracted from the official notice and archived solicitation files. Confirm controlling requirements in the source documents.

Notice information

Read full notice text

8/28/2026: Updates have been made to attachment documents for this solicitation to answer questions posed regarding bid bonds, evaluation criteria and other items. Please review ALL documents as the answers are incorporated into the SOW, Construction RFQ Clauses, and the SF-1442. Further questions should be posed via email to SKCS Sergio Cosby, the listed Contracting Officer's Representative. The contractor shall provide all personnel, equipment, tools, transportation, supervision and other items and services necessary to replace 15 showers in their entirety. All details are included in the SOW.

What changed

Aug 28, 2026 · 1 field changed
DescriptionThe contractor shall provide all personnel, equipment, tools, transportation, supervision and other items and services necessary to replace 15 showers in their entirety. All details are included in the SOW.8/28/2026: Updates have been made to attachment documents for this solicitation to answer questions posed regarding bid bonds, evaluation criteria and other items. Please review ALL documents as the answers are incorporated into the SOW, Construction RFQ Clauses, and the SF-1442. Further questions should be posed via email to SKCS Sergio Cosby, the listed Contracting Officer's Representative. The contractor shall provide all personnel, equipment, tools, transportation, supervision and other items and services necessary to replace 15 showers in their entirety. All details are included in the SOW.

Notice history

Attachments

Open a filename to view the saved source file. If a saved copy is not available yet, FedRoster will continue to the matching SAM.gov notice.

Back to top ↑