Place of performanceMisawa Air Base, JP-02, 033-0021, JPN
Opportunity summary
Source-cited
The Department of Defense is soliciting design-build construction for two membrane storage shelters at Misawa Air Base, Japan, with proposal deadlines set for September 11, 2026. The acquisition will use a Best Value Tradeoff source selection methodology. [4][3]
Key points
Contractor furnishes all labor and materials for design-build requirement. [1]
Two separate awards are intended for Site 1 and Site 2. [4]
Watch items
Proposal submission requires a DoDSAFE link request. [4]
Deliverables include 65% and 100% Design Packages. [2]
Sources
SOW-QKKA261109+(A-1).pdfGENERAL General Description: The Contractor shall furnish all labor, services, materials, supplies, equipment, investigations, studies, supervision, quality control, quality assurance, and travel to achieve this design-build construction requirement.
SOW-QKKA261109+(A-1).pdfEVENT DELIVERY SCHEDULE REVIEW PERIOD REVIEW MEETING Pre-Design/Partnering Meeting Within 14 days after award of this Task Order N/A Misawa Air Base Geotechnical Investigation Within 21 days after award of this Task Order Submit Geotechnical Report with each design submittal N/A Topographic Survey Within 21 days after award of this Task Order N/A N/A 65% Design Package – Part I Within 60 days after the Pre-Design Meeting 14 days Misawa Air Base Revised 65% Design Package – Part 1 based on Review Comment Corrections Within 14 days after the 65% Design Review Meeting N/A N/A Authorization to Commence Construction (Initial Items as described in this SOW) is Issued Within 1 day after the Revised
Solicitation+-+FA502526RB004.pdfThe Offeror shall submit the cost portion of the proposal via the following electronic media: electronic spreadsheet format[Insert media format, e.g., electronic spreadsheet format, electronic mail, etc.] (End of provision) FA502526RB004 Page 37 of 40 Section M - Evaluation Factors for Award 1 Basis for Award This acquisition will be conducted using a Best Value Tradeoff source selection methodology in accordance with FAR Part 15.
Official SAM.gov noticeOfferors must submit a request for a DoDSAFE link to submit their proposals no later than 48hrs before submission deadline.
Generated from the public notice and source-backed solicitation passages. Confirm important requirements in the cited brief and official documents.
Public-source intelligence
Source-backed opportunity brief
8 citations · 5 sources
The government will explain contract requirements and the DB Contractor shall review their proposed project schedule and suggest ways to streamline processes. • Design Review Procedures.
GENERAL General Description: The Contractor shall furnish all labor, services, materials, supplies, equipment, investigations, studies, supervision, quality control, quality assurance, and travel to achieve this design-build construction requirement.
EVENT DELIVERY SCHEDULE REVIEW PERIOD REVIEW MEETING Pre-Design/Partnering Meeting Within 14 days after award of this Task Order N/A Misawa Air Base Geotechnical Investigation Within 21 days after award of this Task Order Submit Geotechnical Report with each design submittal N/A Topographic Survey Within 21 days after award of this Task Order N/A N/A 65% Design Package – Part I Within 60 days after the Pre-Design Meeting 14 days Misawa Air Base Revised 65% Design Package – Part 1 based on Review Comment Corrections Within 14 days after the 65% Design Review Meeting N/A N/A Authorization to Commence Construction (Initial Items as described in this SOW) is Issued Within 1 day after the Revised 65% Design Package – Part 1 is approved by the Government N/A N/A 100% Design Package – Part II Within 21 days after the Revised 65% Design Package 14 days Misawa Air Base Revised 100% Design Within 7 days after the N/A N/A
The Offeror shall submit the cost portion of the proposal via the following electronic media: electronic spreadsheet format[Insert media format, e.g., electronic spreadsheet format, electronic mail, etc.] (End of provision) FA502526RB004 Page 37 of 40 Section M - Evaluation Factors for Award 1 Basis for Award This acquisition will be conducted using a Best Value Tradeoff source selection methodology in accordance with FAR Part 15.
Extracted from the official notice and archived solicitation files. Confirm controlling requirements in the source documents.
Notice information
Read full notice text
Amendment 0001- The purpose of this amendment is to provide the responses to all RFIs submitted by the August 24th deadline. Additional questions will only be accepted if they relate directly to one of the government responses. Follow-up questions must be submitted by August 28th, at 1200 JST. As of now, there will not be an extension in the proposal submission deadline. If an updated SOW and drawings are not provided before the deadline, the answers in the RFIs will take precedence over any conflicting information within the documents. All other terms and conditions remain the same. The 356th Expeditionary Theater Support Group (356 ETSG/CONS) Contracting Office is posting this solicitation for two (2) design-build construction projects to deliver storage shelters at Misawa Air Base, Japan. Complete project requirements, technical specifications, and performance parameters are detailed in the corresponding attached draft Statement of Work (SOW) and project drawings. The following are the ROMs for each site: Project Magnitude / ROM (Rough Order of Magnitude): Site 1 (C-1) Applicable Proposal ROM: $1,000,000 to $5,000,000 Site 2 (A-1) Applicable Proposal ROM: $3,000,000 to $7,000,000 1. Critical Acquisition Milestones & Deadlines Please review the timeline below carefully. Late submissions or questions will not be entertained unless explicitly authorized by the Contracting Officer. All times are in Japan Standard Time (JST). Site Visit (Completed): An organized pre-solicitation site visit was held on 03 August 2026. No secondary or additional site visits will be hosted. Additional RFI Deadline: 21 August 2026 @ 09:00 AM JST. Additional RFIs must be sent via email to both designated POCs (see below) by this deadline to be answered. RFI Responses Posted: The government's RFI responses will be posted as an amendment to this notice no later than 24 August 2026. With the RFIs, the final SOW, drawings and related updates will be provided as well. Proposal Submission Due Date: 11 September 2026 @ 12:00PM JST. Multiple or Single Award: At this time, the Government intends to make two separate awards (one contract for each site) to the responsible Offeror(s) whose proposal(s) provide the best value to the Government. There is a possibility of one single award, but it is not guaranteed. The Government will conduct two distinct evaluations- one for Site 1 and one for Site 2. Offerors may win one site, both sites, or neither site. 2. Important Submission & Evaluation Instructions Request for Information (RFI) Ground Rules: Resulting from the August 3rd site visit, RFIs were submitted and are currently in the process of being answered. Once the formal RFI responses are posted by August 24th, additional questions will only be accepted if they relate directly to one of the published government responses. This process may result in an extended proposal submission window, but does not guarantee additional response time. Proposal Due Date Clarification: Please ignore any system-generated defaults on SAM.gov or within the SF 1447 block that state "03:00 GMT" as the submission deadline. The official, legally binding deadline for proposal receipt is September 11th, 2026, at 12:00 PM JST. Evaluation Guidelines: The full SF 1447 solicitation document contains all guidelines for proposal submission (Section L) and the evaluation factors for award (Section M). These instructions and evaluation factors will only be amended to correct clerical errors or clear up misunderstandings. 3. Contact Instructions Please direct all questions, RFIs, and final proposal submissions* via email to both of the following Points of Contact: SSgt Cameron Smith: cameron.smith.16@us.af.mil SSgt Daniel Callahan: daniel.callahan.7@us.af.mil * For submissions over 10mb, they will not be accepted by our internal e-mail security measures. Offerors must submit a request for a DoDSAFE link to submit their proposals no later than 48hrs before submission deadline.
What changed
Aug 24, 2026 · 2 fields changed
DescriptionThe 356th Expeditionary Theater Support Group (356 ETSG/CONS) Contracting Office is posting this solicitation for two (2) design-build construction projects to deliver storage shelters at Misawa Air Base, Japan. Complete project requirements, technical specifications, and performance parameters are detailed in the corresponding attached draft Statement of Work (SOW) and project drawings. The following are the ROMs for each site: Project Magnitude / ROM (Rough Order of Magnitude): Site 1 (C-1) Applicable Proposal ROM: $1,000,000 to $5,000,000 Site 2 (A-1) Applicable Proposal ROM: $3,000,000 to $7,000,000 1. Critical Acquisition Milestones & Deadlines Please review the timeline below carefully. Late submissions or questions will not be entertained unless explicitly authorized by the Contracting Officer. All times are in Japan Standard Time (JST). Site Visit (Completed): An organized pre-solicitation site visit was held on 03 August 2026. No secondary or additional site visits will be hosted. Additional RFI Deadline: 21 August 2026 @ 09:00 AM JST. Additional RFIs must be sent via email to both designated POCs (see below) by this deadline to be answered. RFI Responses Posted: The government's RFI responses will be posted as an amendment to this notice no later than 24 August 2026. With the RFIs, the final SOW, drawings and related updates will be provided as well. Proposal Submission Due Date: 11 September 2026 @ 12:00PM JST. Multiple or Single Award: At this time, the Government intends to make two separate awards (one contract for each site) to the responsible Offeror(s) whose proposal(s) provide the best value to the Government. There is a possibility of one single award, but it is not guaranteed. The Government will conduct two distinct evaluations- one for Site 1 and one for Site 2. Offerors may win one site, both sites, or neither site. 2. Important Submission & Evaluation Instructions Request for Information (RFI) Ground Rules: Resulting from the August 3rd site visit, RFIs were submitted and are currently in the process of being answered. Once the formal RFI responses are posted by August 24th, additional questions will only be accepted if they relate directly to one of the published government responses. This process may result in an extended proposal submission window, but does not guarantee additional response time. Proposal Due Date Clarification: Please ignore any system-generated defaults on SAM.gov or within the SF 1447 block that state "03:00 GMT" as the submission deadline. The official, legally binding deadline for proposal receipt is September 11th, 2026, at 12:00 PM JST. Evaluation Guidelines: The full SF 1447 solicitation document contains all guidelines for proposal submission (Section L) and the evaluation factors for award (Section M). These instructions and evaluation factors will only be amended to correct clerical errors or clear up misunderstandings. 3. Contact Instructions Please direct all questions, RFIs, and final proposal submissions* via email to both of the following Points of Contact: SSgt Cameron Smith: cameron.smith.16@us.af.mil SSgt Daniel Callahan: daniel.callahan.7@us.af.mil * For submissions over 10mb, they will not be accepted by our internal e-mail security measures. Offerors must submit a request for a DoDSAFE link to submit their proposals no later than 48hrs before submission deadline.Amendment 0001- The purpose of this amendment is to provide the responses to all RFIs submitted by the August 24th deadline. Additional questions will only be accepted if they relate directly to one of the government responses. Follow-up questions must be submitted by August 28th, at 1200 JST. As of now, there will not be an extension in the proposal submission deadline. If an updated SOW and drawings are not provided before the deadline, the answers in the RFIs will take precedence over any conflicting information within the documents. All other terms and conditions remain the same. The 356th Expeditionary Theater Support Group (356 ETSG/CONS) Contracting Office is posting this solicitation for two (2) design-build construction projects to deliver storage shelters at Misawa Air Base, Japan. Complete project requirements, technical specifications, and performance parameters are detailed in the corresponding attached draft Statement of Work (SOW) and project drawings. The following are the ROMs for each site: Project Magnitude / ROM (Rough Order of Magnitude): Site 1 (C-1) Applicable Proposal ROM: $1,000,000 to $5,000,000 Site 2 (A-1) Applicable Proposal ROM: $3,000,000 to $7,000,000 1. Critical Acquisition Milestones & Deadlines Please review the timeline below carefully. Late submissions or questions will not be entertained unless explicitly authorized by the Contracting Officer. All times are in Japan Standard Time (JST). Site Visit (Completed): An organized pre-solicitation site visit was held on 03 August 2026. No secondary or additional site visits will be hosted. Additional RFI Deadline: 21 August 2026 @ 09:00 AM JST. Additional RFIs must be sent via email to both designated POCs (see below) by this deadline to be answered. RFI Responses Posted: The government's RFI responses will be posted as an amendment to this notice no later than 24 August 2026. With the RFIs, the final SOW, drawings and related updates will be provided as well. Proposal Submission Due Date: 11 September 2026 @ 12:00PM JST. Multiple or Single Award: At this time, the Government intends to make two separate awards (one contract for each site) to the responsible Offeror(s) whose proposal(s) provide the best value to the Government. There is a possibility of one single award, but it is not guaranteed. The Government will conduct two distinct evaluations- one for Site 1 and one for Site 2. Offerors may win one site, both sites, or neither site. 2. Important Submission & Evaluation Instructions Request for Information (RFI) Ground Rules: Resulting from the August 3rd site visit, RFIs were submitted and are currently in the process of being answered. Once the formal RFI responses are posted by August 24th, additional questions will only be accepted if they relate directly to one of the published government responses. This process may result in an extended proposal submission window, but does not guarantee additional response time. Proposal Due Date Clarification: Please ignore any system-generated defaults on SAM.gov or within the SF 1447 block that state "03:00 GMT" as the submission deadline. The official, legally binding deadline for proposal receipt is September 11th, 2026, at 12:00 PM JST. Evaluation Guidelines: The full SF 1447 solicitation document contains all guidelines for proposal submission (Section L) and the evaluation factors for award (Section M). These instructions and evaluation factors will only be amended to correct clerical errors or clear up misunderstandings. 3. Contact Instructions Please direct all questions, RFIs, and final proposal submissions* via email to both of the following Points of Contact: SSgt Cameron Smith: cameron.smith.16@us.af.mil SSgt Daniel Callahan: daniel.callahan.7@us.af.mil * For submissions over 10mb, they will not be accepted by our internal e-mail security measures. Offerors must submit a request for a DoDSAFE link to submit their proposals no later than 48hrs before submission deadline.Documents57
Notice history
Solicitation · LatestPosted Aug 24, 2026 · response deadline Sep 11, 2026, 3:00 AM UTC
SolicitationPosted Aug 17, 2026 · response deadline Sep 11, 2026, 3:00 AM UTC
Attachments
Open a filename to view the saved source file. If a saved copy is not available yet, FedRoster will continue to the matching SAM.gov notice.