This RFQ seeks to replace foundation concrete and eight anchor bolts for a BAK-12 Aircraft Arresting System in California. The contract is set aside for SBA Certified Women-Owned Small Businesses, with a response deadline of September 8, 2026. [4]
Key points
Scope includes concrete slab repair and anchor bolt replacement. [2]
Award is based on the quoter offering the best value. [3]
Watch items
Verify deadlines, amendments, and submission instructions in the cited source before responding. [1]
Sources
Solicitation+-+W50S6T26QA036.pdf(iii) Subordinate all subcontractor rights concerning property to which the Government has title under the subcontract to the Government's right to require delivery of the property to the Government if- (A) The Contractor defaults; or (B) The subcontractor becomes bankrupt or insolvent. (5) If the financing payments are in the form of commercial product or commercial service financing payments, the terms of the subcontract or interdivisional order concerning payments- (i) Are constructed in accordance with FAR 32.206(c) and included in a subcontract for a commercial product or commercial service purchase that meets the definition and standards for acquisition of commercial products and comme
Statement+of+Work+BAK12+Anchor+Replacement.pdf3.0 SCOPE AND ORDER OF WORK The Contractor shall furnish all labor, materials, equipment, and engineering services required to complete the concrete slab repair and anchor bolt replacement in the following sequential order: Step 1: Saw Cutting the Bottom Slab 1.
Solicitation+-+W50S6T26QA036.pdfAn award will be provided to the quoter that offers the best value to the government after evaluation in accordance with any factors and subfactors in the solicitation.
Official SAM.gov noticeSet-aside: SBA Certified Women-Owned Small Business (WOSB) Program Set-Aside (FAR 19.15)
Generated from the public notice and source-backed solicitation passages. Confirm important requirements in the cited brief and official documents.
Public-source intelligence
Source-backed opportunity brief
8 citations · 6 sources
(iii) Subordinate all subcontractor rights concerning property to which the Government has title under the subcontract to the Government's right to require delivery of the property to the Government if- (A) The Contractor defaults; or (B) The subcontractor becomes bankrupt or insolvent. (5) If the financing payments are in the form of commercial product or commercial service financing payments, the terms of the subcontract or interdivisional order concerning payments- (i) Are constructed in accordance with FAR 32.206(c) and included in a subcontract for a commercial product or commercial service purchase that meets the definition and standards for acquisition of commercial products and commercial services in FAR parts 2 and 12; (ii) Are in conformance with the requirements of FAR 32.504(g); and (iii) Subordinate all subcontractor rights concerning property to which the Government has title under the subcontract to the Government's right to require delivery of the property to the Government if- (A) The Contractor defaults; or (B) The subcontractor becomes bankrupt or insolvent. (6) If financing is in the form of progress payments, the progress payment rate in the subcontract is the customary rate used by the contracting agency, depending on whether the subcontractor is or is not a small business concern. (7) Concerning any proceeds received by the Government for property to which title has vested in the Government under the subcontract terms, the parties agree that the proceeds shall be applied to reducing any unliquidated financing payments by the Government to the Contractor under this contract.
3.0 SCOPE AND ORDER OF WORK The Contractor shall furnish all labor, materials, equipment, and engineering services required to complete the concrete slab repair and anchor bolt replacement in the following sequential order: Step 1: Saw Cutting the Bottom Slab 1.
An award will be provided to the quoter that offers the best value to the government after evaluation in accordance with any factors and subfactors in the solicitation.
2018-01 REQUIREMENTS FOR SUBMISSION OF PROPOSALS VIA ELECTRONIC MEDIA (JAN 2018) The Offeror shall submit the cost portion of the proposal via the following electronic media: electronic spreadsheet format[Insert media format, e.g., electronic spreadsheet format, electronic mail, etc.] (End of provision) W50S6T26QA036 Page 50 of 52
Extracted from the official notice and archived solicitation files. Confirm controlling requirements in the source documents.
Notice information
Read full notice text
The project involves removal and replacement of a foundation slab of concrete, and replacement of eight anchor bolts to a Barrier Arresting Kit (BAK-12) Aircraft Arresting System. Note: This project may run concurrently with a City of Fresno Runway 11L-29R Reconstruction Contract. Please see attached solicitaiton document, and statement of work for more details. The 144 FW is requesting replacement of foundation concrete and anchor bolts to support a BAK-12 aircraft arresting system. Request for Quote (RFQ) details are provided on the attached solicitation. The 144 FW intends to award a Firm Fixed Price (FFP) contract without negotiations, so offerors are highly encouraged to quote their most advantageous pricing in their initial response. This requirement is being solicited as a Women-Owned Small Business (WOSB) set-aside. The NAICS code for this acquisition is 237310. All prospective quoters must have a Commercial and Government Entity (CAGE) code and be registered with System for Award Management (SAM) at https://www.sam.gov. Offerors shall respond to this RFQ via email. Quotes shall be submitted electronically to the following email addresses: jarrod.sanchez@us.af.mil; justin.scales.1@us.af.mil Any quote, modification, or revision of a quote received after the exact time specified for receipt of quotes is late and will not be considered. Review the RFQ solicitation instructions for quote submission criteria. The Government reserves the right to amend or cancel this RFQ, either before or after the closing date. In the event the Government cancels this solicitation, the Government has no obligation to reimburse an offeror for any costs. Submitted offers shall be valid until September 30, 2026. Site Visit Notice: A site visit will be available on August 27, 2026 (Thursday) at 9am. Approved participants shall meet at the West gate near 5323 E McKinley Ave, Fresno CA 93727. All potential attendees must complete DBIDS pre-enrollment and be listed on the base access form, section CONTRACTOR/VENDOR/VISITOR INFORMATION. https://dbids-global-enroll.dmdc.mil/preenrollui/#/landing-page A background review will be performed and only participants that have been cleared by security will be allowed to attend the site visit. A Real ID or equivalent is also required to access the base. Complete the base access form, consisting of attendee names, citizenship, and DBIDS code (save the 6-digit code accompanied with QR code). The base access form must be provided before the site visit. A foreign national requires 45 business days to review background. If confirmation has not been provided contact our office prior to the site visit to verify base access. Send base access forms to jarrod.sanchez@us.af.mil; justin.scales.1@us.af.mil Notice to Offerors: This effort is a high-priority requirement in support of the National Guard. Funds are not presently available to make award. If funds become available for award and prices are deemed fair and reasonable, it is the Government's intent to make award. This is not a commitment of funds or contract award. As required by 15 U.S.C. § 644(w), implemented by RFO FAR 36.101-4, the following information i sprovided to interested small businesses: (A). The National Guard Bureau (NGB) has no agency-specific policies or procedures applicable to definitization of equitable adjustments for change orders under construction contracts, other than those described at FAR 43.204, DFARS243.204 and Army FAR Supplement (AFARS)5143.204. (B). Data for the prior 3 fiscal years regarding the time required to definitize equitable adjustments for change orders under construction contracts for the NGB is currently unavailable, however data for Department of the Army (which NGB reports to) is listed below: Selected Agency: DEPT OF THE ARMY Time to definitize after receipt of an adequate Change Order Definitization Proposal under Construction Contracts: Number of Change Order Proposals definitized under Construction Contracts 30 days or less: 0 31 to 60 days: 1 61 to 90 days: 0 91 to 180 days: 0 181 to 365 days: 1 Greater than 365 days: 1 After completion of contract performance via a contract modification addressing all undefinitized equitable adjustments received during contract performance: 2