Source-citedThis Firm Fixed Price contract requires inspections for approximately sixty Unfired Pressure Vessels, including air compressors, adhering to ASME code requirements. The work is set aside for Small Businesses and must be performed in Pennsylvania. [2][3]
Key points
- Requires minimum five years experience in boiler/pressure vessel maintenance. [2]
- Contract must ensure vessels are documented as safe to operate. [2]
Watch items
- Contract involves potential access to proprietary Government data. [1]
- Response deadline is September 16, 2026. [3]
Sources
- PERFORMANCE+WORK+STATEMENT+(PWS).docx
Such personnel will be identified at the time of award. **1.11 Identification of Contractor Employees:** ***RESERVED*** **1.12** **Contractor Identification Badges**: Temporary contractor badges will be available during times of services only. **1.13** **Contractor Travel:** ***RESERVED*** **1.14 Other Direct Costs (ODCs):** ***RESERVED*** **1.15 Data Rights: *RESERVED*** **1.16 Non-Disclosure Requirements**:Performance under this contract may require the Contractor to access data and information proprietary to a Government agency, another Government Contractor, or of such nature that its dissemination or use other than as specified in this work statement would be adverse to the interests of
- PERFORMANCE+WORK+STATEMENT+(PWS).docx
Additionally, the contractor is required to have a minimum of five years of experience in the construction, operation, maintenance, and repair of boilers and pressure vessels. **1.3 Scope:** The Contractor shall perform inspections services on approximately sixty (60) Unfired Pressure Vessels (Fifty (50) known at this time) which includes both air compressors and air receiver tanks compliance with American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code requirements, manufacturer’s recommendations, and all other applicable codes as referenced under Part 6 – Applicable Standards. **1.4 Objectives:** Ensure all Unfired Pressure Vessels are inspected and documented as saf
- Official SAM.gov notice
Set-aside: Small Business Set Aside - Total
Generated from the public notice and source-backed solicitation passages. Confirm important requirements in the cited brief and official documents.
Public-source intelligence
Source-backed opportunity brief
8 citations · 6 sourcesSuch personnel will be identified at the time of award. **1.11 Identification of Contractor Employees:** ***RESERVED*** **1.12** **Contractor Identification Badges**: Temporary contractor badges will be available during times of services only. **1.13** **Contractor Travel:** ***RESERVED*** **1.14 Other Direct Costs (ODCs):** ***RESERVED*** **1.15 Data Rights: *RESERVED*** **1.16 Non-Disclosure Requirements**:Performance under this contract may require the Contractor to access data and information proprietary to a Government agency, another Government Contractor, or of such nature that its dissemination or use other than as specified in this work statement would be adverse to the interests of the Government or others.
Scope
Additionally, the contractor is required to have a minimum of five years of experience in the construction, operation, maintenance, and repair of boilers and pressure vessels. **1.3 Scope:** The Contractor shall perform inspections services on approximately sixty (60) Unfired Pressure Vessels (Fifty (50) known at this time) which includes both air compressors and air receiver tanks compliance with American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code requirements, manufacturer’s recommendations, and all other applicable codes as referenced under Part 6 – Applicable Standards. **1.4 Objectives:** Ensure all Unfired Pressure Vessels are inspected and documented as safe to operate in accordance with all applicable standards and the yearly inspection schedules. **Any deemed unsafe to operate shall be immediately brought to the attention of the Government COR and put out of service.** Provide detailed reports of each vessel along with recommendations for any additional maintenance which may be completed by others. **1.5 General Information:** **1.5.1 Quality Control Plan (QCP):** The Contractor shall develop and maintain a QCP to ensure services are performed in accordance with (IAW) this PWS.
Deliverables
Protection of Sensitive Data: Mark and protect internal company data related to this contract (e.g., schedules, deliverables, vulnerability reports) as CUI.
Evaluation
(End of provision) W51AA126QA090 Page 32 of 34 Section M - Evaluation Factors for Award FAR Provisions Incorporated by Reference Number Title Effective Date Alternate Deviation Variation Effective Date 52.217-3 Evaluation Exclusive of Options.
Submission
SUBMISSION OF BIDS OR PROPOSALS Bidders/offerors who hand carry bids or quotes do so at their own risk.
Eligibility
Set-aside: Small Business Set Aside - Total
Place of performance
PA, 18466, USA
Key dates
Posted Aug 26, 2026; Responses due Sep 16, 2026, 2:00 PM UTC; Archive date Oct 1, 2026
Extracted from the official notice and archived solicitation files. Confirm controlling requirements in the source documents.