Place of performanceFort Eustis, VA, United States
Opportunity summary
Source-cited
The Department of Defense seeks a firm-fixed-price contract for Design-Bid-Build construction at the Fort Eustis Dredge Material Management Area. This work involves regrading berms to 36 ft and relocating existing spill boxes. [1]
Key points
Contract is for FEDMMA maintenance requirements. [1]
A prospective contractor shall not be determined responsible or non- responsible solely on the basis of a lack of relevant performance history. d) Have a satisfactory record of integrity and business ethics. e) Have the necessary organization, experience, accounting and operational controls, and technical skills, or the ability to obtain them (including, as appropriate, such elements as production control procedures, property control systems, quality assurance measures, and safety programs applicable to materials to be produced or services to be performed by the prospective contractor and subcontractors).
Failure to submit with the offer satisfactory evidence of the authority of all other persons may be cause for rejection of the offer as invalid or nonresponsive.
Extracted from the official notice and archived solicitation files. Confirm controlling requirements in the source documents.
Notice information
Read full notice text
Amendment 0004: An amendment has been made to Solicitation W9123626BA0008. Please see attachment SF30, Solicitation Amendment W9123626BA008_0004, which incorporates revised Definitive Responsibilty Criteria (DRC) items and extends the bid due date and bid opening date. The Norfolk District, Corps of Engineers is contemplating a firm-fixed-price contract for the Design-Bid-Build construction of maintenance requirements at the Fort Eustis Dredge Material Management Area (FEDMMA), located at JBLE - Eustis with provisions to include Regrading/raising the disposal site berms to an elevation of 36 ft. The berms are currently at elevation 34 ft and have settled in a few places to below 34 ft. The work will also include the relocation of two existing spill boxes 50 - 60 feet into the disposal site. The existing access dirt and stone access ramp will need to be regraded, as well, to meet the new top-of-berm elevation.
What changed
Aug 11, 2026 · 3 fields changed
Response deadline2026-08-18T18:00:00+00:002026-09-15T18:00:00+00:00Archive date2027-07-272027-08-11DescriptionAmendment 0003: An amendment has been made to Solicitation W9123626BA0008. Please see attachment SF30, Solicitation Amendment W9123626BA008_0003, extending the bid due date and bid opening date. The Norfolk District, Corps of Engineers is contemplating a firm-fixed-price contract for the Design-Bid-Build construction of maintenance requirements at the Fort Eustis Dredge Material Management Area (FEDMMA), located at JBLE - Eustis with provisions to include Regrading/raising the disposal site berms to an elevation of 36 ft. The berms are currently at elevation 34 ft and have settled in a few places to below 34 ft. The work will also include the relocation of two existing spill boxes 50 - 60 feet into the disposal site. The existing access dirt and stone access ramp will need to be regraded, as well, to meet the new top-of-berm elevation.Amendment 0004: An amendment has been made to Solicitation W9123626BA0008. Please see attachment SF30, Solicitation Amendment W9123626BA008_0004, which incorporates revised Definitive Responsibilty Criteria (DRC) items and extends the bid due date and bid opening date. The Norfolk District, Corps of Engineers is contemplating a firm-fixed-price contract for the Design-Bid-Build construction of maintenance requirements at the Fort Eustis Dredge Material Management Area (FEDMMA), located at JBLE - Eustis with provisions to include Regrading/raising the disposal site berms to an elevation of 36 ft. The berms are currently at elevation 34 ft and have settled in a few places to below 34 ft. The work will also include the relocation of two existing spill boxes 50 - 60 feet into the disposal site. The existing access dirt and stone access ramp will need to be regraded, as well, to meet the new top-of-berm elevation.
Jul 27, 2026 · 4 fields changed
Response deadline2026-07-23T18:00:00+00:002026-08-18T18:00:00+00:00Archive date2027-07-172027-07-27DescriptionAmendment 0002: An amendment has been made to Solicitation W9123626BA0008. Please see attachment SF30, Solicitation Amendment W9123626BA008_0002, to view the site visit attendance log. Project Summary: The Norfolk District, Corps of Engineers is contemplating a firm-fixed-price contract for the Design-Bid-Build construction of maintenance requirements at the Fort Eustis Dredge Material Management Area (FEDMMA), located at JBLE - Eustis with provisions to include Regrading/raising the disposal site berms to an elevation of 36 ft. The berms are currently at elevation 34 ft and have settled in a few places to below 34 ft. The work will also include the relocation of two existing spill boxes 50 - 60 feet into the disposal site. The existing access dirt and stone access ramp will need to be regraded, as well, to meet the new top-of-berm elevation.Amendment 0003: An amendment has been made to Solicitation W9123626BA0008. Please see attachment SF30, Solicitation Amendment W9123626BA008_0003, extending the bid due date and bid opening date. The Norfolk District, Corps of Engineers is contemplating a firm-fixed-price contract for the Design-Bid-Build construction of maintenance requirements at the Fort Eustis Dredge Material Management Area (FEDMMA), located at JBLE - Eustis with provisions to include Regrading/raising the disposal site berms to an elevation of 36 ft. The berms are currently at elevation 34 ft and have settled in a few places to below 34 ft. The work will also include the relocation of two existing spill boxes 50 - 60 feet into the disposal site. The existing access dirt and stone access ramp will need to be regraded, as well, to meet the new top-of-berm elevation.Documents21
Jul 17, 2026 · 4 fields changed
Response deadline2026-08-04T18:00:00+00:002026-07-23T18:00:00+00:00Archive date2027-07-022027-07-17DescriptionAmendment 0001: An amendment has been made to Solicitation W9123626BA0008. Please see attachment SF30, Solicitation Amendment W9123626BA006_0001, to view the summary of changes, including site visit information. The Norfolk District, Corps of Engineers is contemplating a firm-fixed-price contract for the Design-Bid-Build construction of maintenance requirements at the Fort Eustis Dredge Material Management Area (FEDMMA), located at JBLE - Eustis with provisions to include Regrading/raising the disposal site berms to an elevation of 36 ft. The berms are currently at elevation 34 ft and have settled in a few places to below 34 ft. The work will also include the relocation of two existing spill boxes 50 - 60 feet into the disposal site. The existing access dirt and stone access ramp will need to be regraded, as well, to meet the new top-of-berm elevation.Amendment 0002: An amendment has been made to Solicitation W9123626BA0008. Please see attachment SF30, Solicitation Amendment W9123626BA008_0002, to view the site visit attendance log. Project Summary: The Norfolk District, Corps of Engineers is contemplating a firm-fixed-price contract for the Design-Bid-Build construction of maintenance requirements at the Fort Eustis Dredge Material Management Area (FEDMMA), located at JBLE - Eustis with provisions to include Regrading/raising the disposal site berms to an elevation of 36 ft. The berms are currently at elevation 34 ft and have settled in a few places to below 34 ft. The work will also include the relocation of two existing spill boxes 50 - 60 feet into the disposal site. The existing access dirt and stone access ramp will need to be regraded, as well, to meet the new top-of-berm elevation.Documents32
Jul 2, 2026 · 5 fields changed
TitleFort Eustis Dredge Material Management Area (FEDMMA) construction projectFort Eustis Dredge Material Management Area (FEDMMA)Response deadline2026-07-23T18:00:00+00:002026-08-04T18:00:00+00:00Archive date2026-08-072027-07-02DescriptionThe US Army Corps of Engineers, Norfolk District, is contemplating a firm-fixed-price contract for the construction of maintenance requirements at the Fort Eustis Dredge Material Management Area (FEDMMA), located at JBLE - Eustis with provisions to include Regrading/raising the disposal site berms to an elevation of 36 ft. The berms are currently at elevation 34 ft and have settled in a few places to below 34 ft. The work will also include the relocation of two existing spill boxes 50 - 60 feet into the disposal site. The existing access dirt and stone access ramp will need to be regraded, as well, to meet the new top-of-berm elevation. Contractors should review and follow all bid instructions listed in the solicitation. Site Visit information will be provided in an upcoming amendment to the solicitation. Questions are to be submitted using ProjNet. Bids are to be submitted on the PIEE web site. See web site link within this notice to access PIEE.Amendment 0001: An amendment has been made to Solicitation W9123626BA0008. Please see attachment SF30, Solicitation Amendment W9123626BA006_0001, to view the summary of changes, including site visit information. The Norfolk District, Corps of Engineers is contemplating a firm-fixed-price contract for the Design-Bid-Build construction of maintenance requirements at the Fort Eustis Dredge Material Management Area (FEDMMA), located at JBLE - Eustis with provisions to include Regrading/raising the disposal site berms to an elevation of 36 ft. The berms are currently at elevation 34 ft and have settled in a few places to below 34 ft. The work will also include the relocation of two existing spill boxes 50 - 60 feet into the disposal site. The existing access dirt and stone access ramp will need to be regraded, as well, to meet the new top-of-berm elevation.Documents43
Jun 18, 2026 · 1 field changed
DocumentsNot previously reported4
Jun 18, 2026 · 6 fields changed
TitleFort Eustis Dredge Material Management Area Construction in Newport News, VirginiaFort Eustis Dredge Material Management Area (FEDMMA) construction projectNotice typePresolicitationSolicitationResponse deadline2026-03-24T18:00:00+00:002026-07-23T18:00:00+00:00Archive date2026-04-082026-08-07Set-asideTotal Small Business Set-Aside (FAR 19.5)Small Business Set Aside - TotalDescriptionThe U.S. Army Corps of Engineers (USACE) Norfolk District (NAO) intends to issue an Invitation for Bid (IFB) acquisition for the construction of Maintenance Requirements at the Dredging Material Management Area in Fort Eustis, VA. This procurement will be conducted in accordance with FAR Part 14, Invitation for Bid (IFB). The Government intends to award a firm-fixed-price (FFP) contract. The requirement will be solicited as a 100% Total Small Business Set-Aside. The applicable NAICS code is 237990 for Other Heavy and Civil Engineering Construction, with a Business Standard of $45M. Product Service Code of Z2KF - Repair or Alteration of Dredging Facilities. Disclosure of the magnitude of construction project cost: Between $5,000,000 and $10,000,000. Project Description: Provide labor, material, and equipment to perform the following: This project is for a Design-Bid-Build construction of maintenance requirements at the Fort Eustis Dredge Material Management Area, located at JBLE - Eustis with provisions to include: Regrading/raising the disposal site berms to an elevation of 36 ft. The berms are currently at elevation 34 ft and have settled in some areas to below 34 ft. The berm circumference is approximately 1.5 miles long. The work will also include the relocation of two existing spill boxes 50 - 60 feet from their current location into the disposal site. The existing access dirt and stone access ramp will need to be regraded, as well, to meet the new top-of-berm elevation. All material needed for the project is available within the disposal site. The IFB and accompanying documents will be issued electronically and will be uploaded to PIEE website (https://piee.eb.mil) and accessible via SAM.gov approximately in May 2026. Telephone calls or written requests for the IFB package will NOT be accepted. Prospective bidders are responsible for monitoring SAM.gov to respond to the solicitation and any amendments or other information regarding this acquisition. Prospective bidders are required to be registered in SAM when submitting an offer and shall continue to be registered until time of award, during performance, and through final payment of any contract.The US Army Corps of Engineers, Norfolk District, is contemplating a firm-fixed-price contract for the construction of maintenance requirements at the Fort Eustis Dredge Material Management Area (FEDMMA), located at JBLE - Eustis with provisions to include Regrading/raising the disposal site berms to an elevation of 36 ft. The berms are currently at elevation 34 ft and have settled in a few places to below 34 ft. The work will also include the relocation of two existing spill boxes 50 - 60 feet into the disposal site. The existing access dirt and stone access ramp will need to be regraded, as well, to meet the new top-of-berm elevation. Contractors should review and follow all bid instructions listed in the solicitation. Site Visit information will be provided in an upcoming amendment to the solicitation. Questions are to be submitted using ProjNet. Bids are to be submitted on the PIEE web site. See web site link within this notice to access PIEE.
Notice history
Solicitation · LatestPosted Aug 11, 2026 · response deadline Sep 15, 2026, 6:00 PM UTC
SolicitationPosted Jul 27, 2026 · response deadline Aug 18, 2026, 6:00 PM UTC