The Department of Defense seeks a fully crewed hydraulic pipeline cutterhead dredge for work in New Orleans Harbor and various channels, with a construction magnitude between $10M and $25M. The response deadline for this solicitation is June 12, 2027, and the work will be performed in New Orleans, LA. [4]
Key points
Furnish one fully crewed and equipped hydraulic pipeline cutterhead dredge [1]
Magnitude of construction ranges between $10,000,000.00 and $25,000,000.00 [1]
Watch items
Deliverables include daily reports, submittals, and payment requests [2]
Offerors must complete and submit listed provisions with their quotation [3]
Sources
W912P825B0032+Solicitation.pdf52.236-8 Other Contracts APR 1984 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements APR 1984 52.236-10 Operations and Storage Areas APR 1984 52.236-11 Use and Possession Prior to Completion APR 1984 52.236-12 Cleaning Up APR 1984 52.236-14 Availability and Use of Utility Services APR 1984 52.236-21 Specifications and Drawings for Construction FEB 1997 52.236-26 Preconstruction Conference FEB 1995 52.242-5 Payments to Small Business Subcontractors JAN 2017 52.242-15 Stop-Work Order AUG 1989 52.243-7 Notification Of Changes JAN 2017 52.246-12 Inspection of Construction AUG 1996 52.246-21 Warranty of Construction MAR 1994 52.248-3 Value Engineering-C
W912P825B0032+Solicitation.pdfContractor entries generally include prime and subcontractor information, daily reports, submittals, RFI's, schedule updates, and payment requests.
W912P825B0032+Solicitation.pdfThe offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer.
Generated from the public notice and source-backed solicitation passages. Confirm important requirements in the cited brief and official documents.
Public-source intelligence
Source-backed opportunity brief
7 citations · 6 sources
52.236-8 Other Contracts APR 1984 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements APR 1984 52.236-10 Operations and Storage Areas APR 1984 52.236-11 Use and Possession Prior to Completion APR 1984 52.236-12 Cleaning Up APR 1984 52.236-14 Availability and Use of Utility Services APR 1984 52.236-21 Specifications and Drawings for Construction FEB 1997 52.236-26 Preconstruction Conference FEB 1995 52.242-5 Payments to Small Business Subcontractors JAN 2017 52.242-15 Stop-Work Order AUG 1989 52.243-7 Notification Of Changes JAN 2017 52.246-12 Inspection of Construction AUG 1996 52.246-21 Warranty of Construction MAR 1994 52.248-3 Value Engineering-Construction OCT 2020 52.249-10 Default (Fixed-Price Construction) APR 1984 52.252-2 Clauses Incorporated By Reference FEB 1998 52.253-1 Computer Generated Forms JAN 1991 252.201-7000 Contracting Officer's Representative DEC 1991 252.203-7000 Requirements Relating to Compensation of Former DoD Officials SEP 2011 252.203-7002 Requirement to Inform Employees of Whistleblower Rights DEC 2022 252.203-7003 Agency Office of the Inspector General AUG 2019 252.204-7003 Control Of Government Personnel Work Product APR 1992 252.204-7012 Safeguarding Covered Defense Information and Cyber Incident Reporting MAY 2024 252.225-7048 Export-Controlled Items JUN 2013 252.232-7003 Electronic Submission of Payment Requests and Receiving Reports DEC 2018 252.232-7010 Levies on Contract Payments DEC 2006 CLAUSES INCORPORATED BY FULL TEXT 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) The Contractor shall be required to (a) commence work under this contract within 15 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than the days described in Section 00010-1.4 of the bidding schedule.
(c) A claim under this clause shall not be allowed— (1) For any costs incurred more than 20 days before the Contractor shall have notified the Contracting Officer in writing of the act or failure to act involved (but this requirement shall not apply as to a claim resulting from a suspension order); and (2) Unless the claim, in an amount stated, is asserted in writing as soon as practicable after the termination of the suspension, delay, or interruption, but not later than the date of final payment under the contract. (End of clause) 52.243-4 CHANGES (JUN 2007) (a) The Contracting Officer may, at any time, without notice to the sureties, if any, by written order designated or indicated to be a change order, make changes in the work within the general scope of the contract, including changes-- W912P825B0032 Page 42 of 43 (1) In the specifications (including drawings and designs); (2) In the method or manner of performance of the work; (3) In the Government-furnished property or services; or (4) Directing acceleration in the performance of the work. (b) Any other written or oral order (which, as used in this paragraph (b), includes direction, instruction, interpretation, or determination) from the Contracting Officer that causes a change shall be treated as a change order under this clause; provided, that the Contractor gives the Contracting Officer written notice stating (1) the date, circumstances, and source of the order and (2) that the Contractor regards the order as a change order. (c) Except as provided in this clause, no order, statement, or conduct of the Contracting Officer shall be treated as a change under this clause or entitle the Contractor to an equitable adjustment. (d) If any change under this clause causes an increase or decrease in the Contractor's cost of, or the time required for, the performance of any part of the work under this contract, whether or not changed by any such order, the Contracting Officer shall make an equitable adjustment and modify the contract in writing.
The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer.
Extracted from the official notice and archived solicitation files. Confirm controlling requirements in the source documents.
Notice information
Read full notice text
Mississippi River, New Orleans Harbor and Various Channels Cutterhead Dredge No. 3-2025 (OM25032) The work consists offurnishing one fully crewed and equipped hydraulic pipeline cutterhead dredge. Work will be performed in the New Orleans Harbor Reach of the Mississippi River, adjacent lock forebays of the Gulf Intracoastal Waterway, Bayou Lafourche, Baptiste Collette, Houma Navigation Canal, and Barataria Bar Channel. The magnitude of construction range for this Dredge project is between $10,000,000.00 and $25,000,000.00. The Solicitation will be established and a bid opening date will be established in a future amendment. The solicitation documents for this procurement is posted on Sam.gov. You can access these files from a link located on Sam.gov (www.SAM.gov). You will need the adobe acrobat reader for .pdf files (www.adobe.com) in order to open most files posted by the New Orleans District. You are encouraged, for marketing purposes, to register as an Interested Vendor in beta.Sam.gov (www.beta.SAM.gov). This can be done by clicking on the solicitation title and clicking on the button that says Register as an Interested Vendor and entering your business information. Offerers are also encouraged to post notices of prospective subcontracting opportunities on the Small Business Administration's Subnet, at http://web.sba.gov/subnet. Offerers must be registered with the System for Award Management (SAM), in order to receive a Government contract award. To register, the SAM Internet address is: http://www.sam.gov. The Contract Specialists for this solicitation is Cori A.Caimi at 504-862-1352 (email Cori.A.Caimi@usace.army.mil) or Bambi Raja at 504-862-1499 (email Bambi.l.raja@usace.army.mil).
What changed
No field-level changes were detected between related notices.
Notice history
Solicitation · LatestPosted Jun 12, 2025 · response deadline Jun 12, 2027, 4:00 PM UTC