Scope
SCOPE OF WORK Unless specifically noted otherwise in this Specification Section or in the base MATOC contract Volume 1 of 2 itself, all requirements of the base MATOC contract Volume 1 of 2 shall apply to this Task Order.
DEPT OF DEFENSE · DEPT OF THE ARMY · W072 ENDIST LOUISVILLE
This solicitation is for Design and Construction Services for the FY26 National Roofing Program (NRP) Project #10 in Wilmington, NC, referencing existing IDIQ contracts. The response deadline is September 17, 2026, and the solicitation is for the NRP MATOC Pool Only. [5]
All contractor employees with access to a Government info system must be registered in the ATCTS at commencement of services and must successfully complete the DoD Information Assurance Awareness prior to access to the information system and annually thereafter.
SCOPE OF WORK Unless specifically noted otherwise in this Specification Section or in the base MATOC contract Volume 1 of 2 itself, all requirements of the base MATOC contract Volume 1 of 2 shall apply to this Task Order.
2.2.5 Design Milestone Schedule Notice to Proceed (NTP) Day 0 Design Quality Control Plan (DQCP) NTP + 14 Days Charette Report (FIO no review) NTP + 60 Days Final Submittal NTP + 120 Days Final Plan in Hand Meeting (on-site) NTP + 138 Days Corrected Final Submittal NTP + 152 Days Certified Final Submittal NTP + 160 Days 2.3.
Submit your proposal by email to Laura.Phillips-Payne@usace.army.mil.
Place of performance: Wilmington, NC, USA
Generated from the public notice and source-backed solicitation passages. Confirm important requirements in the cited brief and official documents.
All contractor employees with access to a Government info system must be registered in the ATCTS at commencement of services and must successfully complete the DoD Information Assurance Awareness prior to access to the information system and annually thereafter.
SCOPE OF WORK Unless specifically noted otherwise in this Specification Section or in the base MATOC contract Volume 1 of 2 itself, all requirements of the base MATOC contract Volume 1 of 2 shall apply to this Task Order.
2.2.5 Design Milestone Schedule Notice to Proceed (NTP) Day 0 Design Quality Control Plan (DQCP) NTP + 14 Days Charette Report (FIO no review) NTP + 60 Days Final Submittal NTP + 120 Days Final Plan in Hand Meeting (on-site) NTP + 138 Days Corrected Final Submittal NTP + 152 Days Certified Final Submittal NTP + 160 Days 2.3.
The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations.
Submit your proposal by email to Laura.Phillips-Payne@usace.army.mil.
Wilmington, NC, USA
Posted Sep 1, 2026; Responses due Sep 17, 2026, 6:00 PM UTC; Archive date Oct 2, 2026
Extracted from the official notice and archived solicitation files. Confirm controlling requirements in the source documents.
*************************************Amendment 0001 to revised Site Visit date from 08 September to 09 September. ******************************************************* Design and Construction Services for the FY26 National Roofing Program (NRP) Project #10 - NC106 Wilmington, North Carolina. ****This Solicitation is for the NRP MATOC Pool Only**** Reference is made to your Indefinite Delivery Contract Numbers W912QR24D0054 - W912QR24D0063, Indefinite Delivery Indefinite Quantity (IDIQ), Design-Build Multiple Award Task Order Contract (MATOC) for Building Envelope, Roof Repair and Replacement Construction in Support of the U.S. Army Reserves National Roofing Program (NRP), Army, and Air Force Reserve Sections.
Open a filename to view the saved source file. If a saved copy is not available yet, FedRoster will continue to the matching SAM.gov notice.